Fast-Track Construction of 60 TPH Pusher-Type Reheating Furnace in Jordan
On November 25, 2025, the foundation was officially handed over to us by the client.
Just two weeks later—on December 8, 2025—the steel structure was fully erected.
We are now on schedule to complete the entire furnace installation within 40 days from the handover date, demonstrating our commitment to speed, efficiency, and reliable execution. -

Russia Dual-Furnace Project Progresses Smoothly
First Conventional Heating Furnace Completed and Awaiting Commissioning
-

HT Furnace‘s Furnace Project in Cairo
Cairo, Egypt – HT Furnace is currently commissioning a new conventional combustion reheating furnace for Egyptian company EDL.
-

Dubai AGSI: New Projects
Dubai's AGSI Expands Production with Second Furnace from HT Furnace Following Successful Commissioning